Forum Post: To control flow direction

$
0
0
Hi! I'm working in Watergems and the scheme of my model is attached. The water comes from the reservoir and is consumed in the node J-1 passing through the turbine. When the demand in J-1 is higher than the maximum flow of the turbine (96l/s) the bypass starts to work and the pipe P44 opens. My problem is that when it happens I want that the turbine  continues working and only the "extra" amount of water goes through the bypass. But it is not happening, instead, when the demand is higher than the turbine max flow all the water goes to the bypass and none  thought the turbine.  Is there any way to control that? Thank you in advance,  Teresa