Forum Post: Flushing II (Pipe Run)

$
0
0
Hello   As photos attched, there is a ‘Flushibg’ has been defined for the network. As you see P-4 and ISO-2 is closed and water must flows from Pipe Run path (from ‘Reservoir’ to P-1 and P-2 and P-3 and then J-3). But when Event-1 is Run, ‘result Browser’ shows that ‘Pipe Length Met target’ is equal to 1000 m. It must be 600 m (=100+200+300) because P-4 is closed and pipe Run does not path through P-4. How this can be explained? Sim